Turbine ready to start since yesterday morning
- Generator H2 pressure 500 kPa, purity
99.8%, ready for full speed and excitation
- System ready for pre-synchronization electrical
tests
- Plant in by-pass operation since
yesterday 21h00
- Start of the turbine planned 6h00 (in
stand-by up to now due to HITACHI boiler mills problems)
11:02 - ST @2200RPM
11:35 - Warm-up completed ramping to 3000RPM
11:32 - Turbine Trip
11:42 - Turbine start to ramp up (@1800RPM)
- We found out some problems with speed
control (STSN will investigate)
- 13h30 Stop the turbine
- Turning gear is not taking over (STSN
will investigate)
-
16:31 - start to ramp up Turbine Speed16:50 - Turbine @3000RPM
17:15 - Stop Turbine
17:300 - LP By-Pass in operation
Boiler will run with 2 mills during the night (no oil burners)
- Next start tomorrow 5h00
-