FORECAST PROGRAMME
ACTUAL:
Status 11/03/2015 5:30
-
Hitachi
PTW for crack repair closed @ 5:00
-
Boiler
filling ongoing
-
Turbine
start expected @ 14:00
-
Synchronization
expected @ 14:15
ACTUAL@ 24:00
-
Unit
was synchronized @ 16:52
-
18:06
Turbine trip due to LP heater 1 level transmitter problem
-
18:15
Synchronization and load increase up to 300MW with 2 mills in service
-
22:00
One mill trip, load reduced to 180MW
-
Draft
group trip due to gas air heater
-
Second
mill trip
-
22:52
Turbine trip due to high exhaust temperature HP
-
GCB
didn’t open, and we get low reverse power (reverse power was not detected by
gen protection device)
-
The
case is under investigation
LOAD PROFILE FROM DCS