| Unit 6 Optimisation Summary Programme | ||
| Average Load (MW) | Activity | |
| Lower limit | Upper limit | |
| 200 | 400 | Unit on load and stable - Mill 40 commissioning (hot) |
ACTUAL:
- Situation at 7:00 Boiler
drained
-
Aux
boilers drained (Aux boilers also contaminated)
-
7:00 1st
aux boiler Start
-
Next
turbine start expected 07/03/2015 13:00
- 20:00 Boiler
and turbine ready to start after several drains due to high conductivity
-
Expected
boiler start 08/03/2015 4:00