Thursday, April 16, 2015

16/04/2015



-          Boiler Feed water flow tuning improved
-          11:03 Synchronisation and load up 356 MW. Boiler  and feed water flow tuning.
-          14:10 Unit trip due to Boiler main steam temperature drop (Turbine protection): Boiler load control problem.
-          18:00 Synchronisation: load steady (around 200 MW) over night.