06:00 - Turbine on Baring
06:12 - STG @3000RPM
Waiting for electrical test (ESKOM)
07:23 - STG Trip on Boiler Temp Protection
07:55 - reset STG Protection
2 trips due to boiler temperature (Hitachi)
10h00 Start of electrical test
12:01 - Boiler Tripped
12h30 Boiler trip (Ash level High – Hitachi/ESKOM)
13:07 - STG on Baring
Electrical test step : Excitation at 0 Amp
-
Expected
boiler start 21h00
23:26 Fires in00:10 - LP By-Pass in operation
00:55 - Mill 20 in service
xpected turbine start tomorrow 6h00 – 6h15