Turbine at 3000 RPM forecasted tonight 18h00!
2h45 CT replacement complete
3h00 Aux boiler started
-
8h00
boiler filling
-
10h00
Boiler must be drained due to high conductivity
-
15h00
Boiler start16h00 : boiler 20 burners on
: steam water cycle in by-pass operation (waiting for water and steam quality)
17h50 Turbine start
-
18h00
Turbine @ 3000 RPM – ready for electrical test
20h00: Boiler trip; HP by-pass issue.Several attempts to restart the boiler were performed unsuccessfully.
23h00: Hitachi investigating..