| Unit 6 Optimisation Summary Programme | ||
| Average Load (MW) | Activity | |
| Lower limit | Upper limit | |
| 200 | 300 | Unit on load, 2 mills in services, commission HP and LP heaters |
-
ACTUAL
-
7:00
Turbine ready to start as per Eskom schedule, boiler not ready due to problems
at the mills (no details given to us)
-
7:40
One mill started
-
9:36
Turbine start
-
9:42
Turbine @ 3000 RPM
-
9:51
Synchronization
-
10:26
Load 190 MW
-
10:48
Load 230 MW
-
Commissioning
of LP Heaters 2 and 3
-
11:41
Second mill in service
-
12:16
Load 300 MW
-
12:25
Mill 30 trip