Saturday, March 7, 2015

07/03/2015



Unit 6 Optimisation Summary Programme
Average Load (MW) Activity
Lower limit Upper limit
200 400 Unit on load and stable - Mill 40 commissioning (hot)

ACTUAL:


-          Situation at 7:00 Boiler drained
-          Aux boilers drained (Aux boilers also contaminated)
-          7:00 1st aux boiler Start
-          Next turbine start expected 07/03/2015 13:00

-          20:00 Boiler and turbine ready to start after several drains due to high conductivity
-          Expected boiler start 08/03/2015 4:00
-          Expected turbine start 08/03/2015 7:00

LOAD PROFILE FROM DCS 