Unit 6 Optimisation Summary Programme
Average Load (MW) Activity
Lower limit Upper limit
200 400 Unit on load and stable - Mill 50 commissioning (hot)



Program of the day, start 2 mills, increase load up to 300 MW and stabilize

-          7:00 Boiler ready, one mill running, system in by-pass operation
-          7:30 Turbine start
-          7:36 Turbine @ 3000 RPM
-          7:40 Synchronization
9:00 Load 180 MW
-          18:00 Plant was running @ 180MW continuously
-          Normal shut down in order to clean the FWT tomorrow morning